Engineering, Procurement, Construction & Commissioning of 33kV over head line extension to the existing power infrastructure of OGC, to provide power to BVS-01 block valve station.
Punjlloyd was executing the Engineering, procurement and construction of this project of Oman gas Company S.A.O.C. The scope of work in the above contract includes all activities necessary and required in and for the completion of instrumentation works, testing and pre-commissioning of the block valve stations.
Location | : Saih Rawal |
Client | : Oman Gas Company |
Year | : 2009 |
HSE Status | : No LTI |
Major Achievement | : Managing Interface between PDO & OGC and Achievement of shutdown deadline without any oil deferment |
Complete Electrical & Instrumentation Installation activities for the completion of the Project. Also assisting the Pre-commissioning & Commissioning activities.
Electrical Works
Instrumentation Works
Location | : Al Gubrah |
Client | : International Water Treatment LLC |
Contract | : Orbital Projects & Services LLC |
Year | : 2014 |
Location | : PDO Rima |
Client | : Rima Water Treatment Projects (RWTP) |
Main Contractor | : Orbital Projects & Services LLC |
Package | : Electrical Package |
Year | : August 2021 – March 2022 |
Orbital Projects & Services LLC’s Scope include Installation of Electrical, Instrumentation, Control & Automation works related to the completion of the project.
PROJECT DESCRIPTION
ORPC Co-Generation Power plant is a power facility to provide clean and reliable energy to the refinery and its customers. This facility also ensures the reliable supply of steam, desalinated water, process water and instrument air to the refining units.
The project includes 2x25 MW Gas Turbine, 2x100 TPH HRSG, Supplementary Firing Aux. Boiler, Desalination Plant, Polishing Plant, Fuel Gas Conditioning, Warehouse Re-location etc.
Location | : Sohari |
Client | : Oman Oil Refineries and Petroleum Industries Company (Orpic) |
Contract | : HICO / Orbital Projects & Services LLC |
Year | : 2010 - 2011 |
PROJECT DESCRIPTION
Haya water responsible for the waste management in sultanate’s capital, is supporting the development of the nation by implementing the Muscat wastewater master plan in the Governorate of Muscat. A’seeb waste water project is a primary element of Muscat wastewater master plan. There is wastewater treatment plant, 3 nos of main pumping stations, recycled water facilities at Al-Khoudh & Al-Mobellah as part of this project. The plant designed to treat 80,000 cubic meters of sewage waste water per day. The plant utilizes special technology known as Sequential Batch Reactor (SBR) process and ultra-filtration. The process selection was done based on available processes in international market. The main Sewage Treatment Plant (STP) unit will be located at Seeb about 45 km from Muscat. The STP will be designed to have odorless treated water output which will be mainly used for irrigation purposes.
ORBITAL SCOPE
Electrical & Instrumentation Installation activities for the completion of the Project. Also assisting the Pre-commissioning & Commissioning activities.
Electrical Works
•Installation of Transformers (2 nos of 33/11kV, 4 nos of 11/0.433kV Oil type & 2 nos of 11/0.433kV Dry type)
• Installation of 33kV MV Panel, 11kV Panel, Control & Relay panels etc
• Installation of 11kV capacitor Bank.
• Installation of 415v LV Panels & MCC Panels (Make: ABB & Schneider)
• Installation of UPS System, Battery Chargers & Battery Racks (10 nos)
• Installation of different type of DBs’, Isolators etc.
• Laying of Power & Control cables (Approximately 1,015 Runs)
• Glanding & Termination of Power & Control cables (Approximately 10,200 termination points)
• Fabrication & Installation of Cable trays/Ladders (Both HDG & FRP type) & Conduits (Both GI & PVC)
• Fabrication, Painting & Installation of Structural Supports for cable trays/Ladders, Panels etc.
• Installation of lighting system & receptacles, switches, sockets etc.
• Installation of Area Lighting street Light poles including the installation of Foundations.
• Installation of the Lightning protection & Earthing system
• Installation of Fire alarm system, Telephone & Public address system.
• Excavation & back filling including pre-padding & Post-padding of Cable trenches.
Instrumentation Works
• Installation of DCS Panels (Make: Honeywell)
• Installation of Field Instruments such as Pressure Transmitters, Temperature Transmitters, Diff. Pressure Transmitters, flow transmitters etc (Make: Honeywell)
• Installation of Field junction boxes, LCPs
• Laying of Instrument cables (Approximately 2,950 Loops)
• Glanding & termination of Instrumentation cables (Approximately 32,500 Termination points)
• Laying, splicing & OTDR testing of Fiber Optic cables.
• Installation of Cable trays (Both HDG & FRP type)
• Installation of Impulse tubing for the Instruments such as Transmitters & Control Valves
• Fabrication, Painting & Installation of Structural Supports for cable trays, Inst. Panels, Junction Boxes, Instruments etc.
• Installation of CCTV system, Access control system.
Location | : A'Seeb |
Client | : Haya Water |
Main Contract | : Hyundai Rotem Company |
Subcontractor | : Orbital Projects & Services LLC |
Year | : 2013 - 2014 |